πVolume Estimation Challenge: Material Moved
π― Objective
Calculate how much material is moved:
- Per bucket/pass
- Per hour of operation
π Key Formula
Volume per pass = Bucket Capacity × Fill Factor
Volume per hour = Volume per pass × Cycles per hour
π Fill Factor Guide
(Used to adjust for real-world loading efficiency)
|
Material Type |
Fill Factor |
|
Loose sand |
1.00 |
|
Gravel |
0.90 |
|
Clay |
0.80 |
|
Wet sticky soil |
0.70 |
π§© Game Round 1: Per Pass Calculation
Problem 1
An excavator has:
- Bucket capacity: 1.5 m³
- Material: gravel (0.90 fill)
π What is the volume moved per pass?
Problem 2
A loader has:
- Bucket capacity: 3.0 m³
- Material: wet soil (0.70 fill)
π Volume moved per pass?
Problem 3
A backhoe moves:
- Bucket capacity: 0.8 m³
- Material: clay (0.80 fill)
π Volume moved per pass?
β±οΈ Game Round 2: Per Hour Production
Problem 4
Excavator cycles: 120 cycles/hour
From Problem 1 result
π What is the total hourly volume?
Problem 5
Loader cycles: 75 cycles/hour
From Problem 2 result
π Total hourly volume?
Problem 6
Backhoe cycles: 90 cycles/hour
From Problem 3 result
π Total hourly volume?
π§ Bonus Round (Advanced)
Problem 7
A bulldozer pushes:
- Blade capacity: 5 m³
- Fill factor: 0.85
- Cycles: 60 per hour
π Total volume per hour?
Problem 8
A haul truck carries:
- Capacity: 20 m³ per load
- Loads per hour: 8
- Efficiency factor: 0.95
π Total volume per hour?